When Is the Best Time to Purchase and Install a Solar System for a New Building

0 admin 2025-01-13 16:59:46

FAQ: When Is the Best Time to Purchase and Install a Solar System for a New Building?


Question: For new constructions such as houses, factories, malls, schools, hospitals, churches, etc., when is the best time to purchase a solar system?
Answer: To ensure that the solar system integrates seamlessly with the building construction, it’s essential to plan the procurement and installation at the right time. Below are our recommended timelines:

Recommended Timeline for Purchase and Installation
Contact TANFON During the Foundation Stage


Why?
Reaching out to us during the foundation phase ensures that the subsequent wiring, equipment placement, and solar system layout can be fully considered during the construction process.
Install the Solar System During the Electrical and Plumbing Phase


Why?
Installing the solar system wiring during the electrical and plumbing phase allows for a more streamlined and aesthetically pleasing integration. Equipment placement, switches, and wiring paths can be pre-planned, ensuring a seamless fit once the building is complete.

Timeline Backward Planning
To accurately schedule the purchase and installation, we recommend working backward from your target installation date. Here’s how:


System Production Time:
Depending on the system size, production typically takes 10-35 days.
Small systems (20KW-50KW): About 10-25 days for production.
Large systems (100KW-200KW): About 25-35 days for production.


Shipping Time:
Shipping to African markets usually takes 25-45 days, depending on the destination and shipping method.
For example, shipping to Nigeria typically takes 25-30 days, while shipping to East Africa may take 35-45 days.


Customs Clearance Time:
1.Customs clearance usually takes 5-15 days, depending on the policies of the destination country.

Practical Timeline Example

If your target date for electrical and plumbing installation is mid-April 2025, with solar system installation happening simultaneously:
Mid-April: Begin on-site wiring and system installation.
Early April: Solar system equipment should have cleared customs and be ready on-site.
Late February to Early March: Ship the solar system to allow adequate transportation time.
Mid-February: Place your order with TANFON to allow sufficient time for production.

Why Contact TANFON Early?

Optimized Design: Early consultation allows us to design the solar system layout tailored to your building’s specific needs, optimizing equipment placement and wiring paths.
Save Time and Costs: Simultaneous installation during construction avoids duplicate work, increasing efficiency and reducing additional construction costs.
Aesthetic Integration: Installing the solar system before the building is completed ensures a clean, professional, and visually appealing finish.

If you’re planning to install a TANFON solar system for your new building, contact our sales manager anytime! We will help you plan the right timeline and provide expert guidance on procurement and installation.

< >

TANFON SOLAR: Cooperation with Nigerian Senator MR.MORO

8MW Solar System for City TINE, Valued by President of Chad

1MW/1.8MWh solar energy system electricity for villages in Congo

The King of the Democratic Republic of the Congo has provided a solar energy storage power station system for the village of Bunkeya to meet the electricity needs of 2500 small households in the village. As the village currently lacks access to the grid, the King requested the design of a 1MW solar panel system paired with a 1.8MWh lithium battery storage system to power the entire village.

Tanfon Solar IoT APP

China Safety Solar system Leading Brand

Dealer Policy

loading